ADOSH-SF Code of Practice CoP 46.1 - Construction of Water Wells

الإشارة الرسمية الجهة المُصدرةADPHC - Code of Practices → الإصدار / النشر / النفاذ— · — · — عدد الجريدة الرسمية الفئةguideline آخر فهرسة11 Jul 2026
المصدر الرسمي ↗ English

Abu Dhabi Occupational Safety and
Health System Framework
(ADOSH-SF)
Code of Practice
CoP 46.1 – Construction of Water Wells
Version 4.0
July 2024

ADOSH-SF – Codes of Practice - CoP 46.1 – Construction of Water Wells
Version 4.0 – 15 th July 2024
Page 2 of 22
Table of Contents
1. Introduction ....................................................................................................................................................... 3
2. Training and Competency ............................................................................................................................. 6
3. Requirements .................................................................................................................................................... 7
3.1 Roles and Responsibilities ................................................................................................................. 7
3.2 Planning and Assessment.................................................................................................................. 9
3.3 General Construction Requirements .............................................................................................. 9
3.4 Plant and Equipment ......................................................................................................................... 15
3.5 Machine Guarding ............................................................................................................................... 15
3.6 Visual and Hand Signals ................................................................................................................... 15
3.7 Lone Working and/or in Remote Locations ............................................................................... 15
3.8 Hazardous Substances...................................................................................................................... 15
3.9 Waste Management ........................................................................................................................... 16
3.10 Dust and Toxic Gases ........................................................................................................................ 16
3.11 Heat Stress and Exhaustion ........................................................................................................... 16
3.12 Noise and Vibration............................................................................................................................ 16
3.13 Lighting................................................................................................................................................... 17
3.14 First Aid .................................................................................................................................................. 17
3.15 Fire Prevention and Control ............................................................................................................ 17
3.16 Emergency Management ................................................................................................................. 18
4. References ....................................................................................................................................................... 19
5. Document Amendment Record ................................................................................................................. 20

ADOSH-SF – Codes of Practice - CoP 46.1 – Construction of Water Wells
Version 4.0 – 15 th July 2024
Page 3 of 22
1. Introduction
(a) This Code of Practice (CoP), prepared in consultation with the concerned authorities,
applies to all employers within the Emirate of Abu Dhabi.
(b) This CoP provides the minimum OSH requirements for the construction of water wells
in Abu Dhabi for licensed drilling contractors (entities).
(c) This CoP establishes the requirements and standards so that the risks associated with
the construction of wells are assessed, and that control measures in accordance with
the hierarchy of controls are implemented to prevent injury, illness and disease to
persons who might be exposed to risks arising from well construction activities.
(d) This CoP does not include specific requirements for water quality sampling, yield
testing and final utilization of the well water, which shall be as established by
concerned local and federal authorities.
(e) “Principal Contractor” when used in this CoP refers to the main contractor overseeing
the operation and responsible for activities undertaken on the site within the Building
and Construction Sector. Refer
to ADOSH-SF – CoP 53.0 – OSH Management during
“Construction Work”.
(f) In prescribing the minimum acceptable OSH requirements for well construction, this
CoP is not intended to be viewed as a substitute for formal training.
(g) Definitions applicable to this CoP:
(i) Alignment – the horizontal deviation between the actual well centre line and a
straight line representing the ideal center line.
(ii) Annular Space – the ring-like space between the well casing and the outer well
casing or well hole.
(iii) Aquifer – a geological formation, group of formations, or part of a formation,
capable of transmitting and yielding quantities of water.
(iv) Artesian Well – a well in an aquifer where the groundwater is confined under
pressure, so that the water level in the bore will rise above the top of the aquifer
and ground level (a flowing well).
(v) Casing – a tube used as a temporary or permanent lining for a well.
(vi) Cement Grout – a fluid mixture of Portland cement and water of a consistency
that can be forced through a pipe and placed as required.
(vii) Centralizer – a tool used to centre the casing in the hole.
(viii) Construction - the entire process of creating a well, from initial drilling and
inserting the surface casing through to insertion of a screen and developing the
aquifer prior to installing a pump.
(ix) Decommissioned Well - a well, the purpose and use of which have been
permanently discontinued.
(x) Development – the removal of sand and other fines (including drilling mud) from
the aquifer immediately surrounding the well and creating a filter zone around
the well that prevents further movement of aquifer particles into the well.

ADOSH-SF – Codes of Practice - CoP 46.1 – Construction of Water Wells
Version 4.0 – 15 th July 2024
Page 4 of 22
(xi) Drilling Fluid - a medium used to lubricate the drill bit and stabilise the formation,
control groundwater, and remove the drill cuttings from the hole as drilling takes
place.
(xii) Drilling Operations - the drilling, construction, development, maintenance and
rehabilitation, and decommissioning of a well.
(xiii) Free Flowing Well - a well from which groundwater is discharged at the ground
surface without the aid of pumping.
(xiv) Formation - a bed or deposit composed throughout of substantially the same
kind of rock; a lithologic unit. Each different formation is given a name.
(xv) Formation Pressure (Head) - energy contained in a water mass, produced by
elevation, pressure, or velocity.
(xvi) FRE – Fibreglass-reinforced epoxy — a composite material composed of glass
fibres and epoxy resin.
(xvii) FRP – Fibreglass-reinforced plastic — a composite used for well casing or riser
pipe that is inert to most naturally occurring substances.
(xviii) Gravel Pack - granular material introduced into the annulus between the well
hole and a casing or perforated lining to prevent or control the movement of
finer particles from the aquifer into the well.
(xix) Groundwater – (underground water) water that is held in the ground.
(xx) Grout – a fluid mixture of cement and water of a consistency that can be pumped
through a pipe, to which other additives (eg. bentonite) may be added to
enhance its properties. Sometimes called “cement grout” or “cement slurry”.
(xxi) Grouting - the operation of placing or pumping a grout into an annular space or
cavity.
(xxii) Head - see formation pressure.
(xxiii) Headwork’s - An assembly bolted to the casing to control the well, to provide
access and protection.
(xxiv) Hydrogeological Properties - the properties of formations that control the
movement and storage of groundwater.
(xxv) Permeability - the capacity of a porous medium for transmitting water.
(xxvi) Plumbness – the horizontal deviation (drift) of the well center line from true
vertical.
(xxvii) Production Zone - the zone within the target formation that produces the water
supply requirements for the well.
(xxviii)Pumping Level - the water level in the well when pumping is in progress.
(xxix) Rehabilitation – the restoration of a well to its most efficient condition using a
variety of chemical or mechanical techniques, which may include replacing the
production casing and/or screens.
(xxx) Screen - a special form of well liner used to stabilise the aquifer or gravel pack
while allowing the flow of water through the well into the casing and permitting
development of the screened formation by an appropriate process.

ADOSH-SF – Codes of Practice - CoP 46.1 – Construction of Water Wells
Version 4.0 – 15 th July 2024
Page 5 of 22
(xxxi) Shoe – an extension fitted to the end of the casing, commonly a drive shoe (for
advancing the casing) or a float shoe (use for grouting).
(xxxii) Test Well - completed well for pumping to obtain information on capacity,
groundwater quality, geological and hydrological conditions, and related
information.
(xxxiii)Test Hole - a hole used only to obtain information on groundwater quality and/or
geological and hydrological conditions.
(xxxiv) Transmissivity - the rate at which water of the prevailing kinematic
viscosity is transmitted through a unit width of an aquifer under a unit hydraulic
gradient, expressed in square meters per day. Note: Transmissivity is equal to
the hydraulic conductivity multiplied by the thickness of the aquifer.
(xxxv) Water Table – the surface of saturation in an unconfined aquifer at which the
pressure of the water is equal to that of the atmosphere.
(xxxvi) Well – a hole sunk into the ground and completed for the abstraction of
water or for water observation purposes.

ADOSH-SF – Codes of Practice - CoP 46.1 – Construction of Water Wells
Version 4.0 – 15 th July 2024
Page 6 of 22
2. Training and Competency
(a) Employers shall ensure that OSH training complies with the requirements of:
(i)
ADOSH-SF – Element 5 – Training, Awareness and Competency.
(ii)
ADOSH-SF – Mechanism 7.0 – Occupational Safety and Health Practitioner and
Service Provider Registration.
(b) Employers shall ensure personnel required to implement the requirements of this CoP
are trained in construction of wells and understand the risks associated and the
control measures implemented by the employer.
(c) Employers shall ensure all employees involved in the construction of water wells shall
be trained to recognise and respond to hazards associated with this type of work.
(d) Training shall be tailored to the specific requirements of the jobsite and include any
unique issues or requirements and the following subjects shall be part of the
employee training program:
(i) identified hazards and risks;
(ii) site rules and prohibited activities;
(iii) specific plant and equipment operations;
(iv) devised safe methods of working;
(v) site access and egress;
(vi) lighting requirements (if applicable);
(vii) work in remote areas and communications;
(viii) personal protective equipment;
(ix) emergency procedures; and
(x) fire prevention and protection.
(e) Employers shall maintain a record of the required training that contains the following
information:
(i) trainee name and ID number;
(ii) trainee Emirates ID number;
(iii) subject(s) of training;
(iv) training provider;
(v) date(s) of training; and
(vi) person(s) providing the training.

ADOSH-SF – Codes of Practice - CoP 46.1 – Construction of Water Wells
Version 4.0 – 15 th July 2024
Page 7 of 22
3. Requirements
3.1 Roles and Responsibilities
3.1.1 Employers
(a) Employers shall undertake their roles and responsibilities in accordance with the
general requirements of
(i) ADOSH-SF – Element 1 – Roles, Responsibilities and Self-Regulation Section
3.2.5; and
(ii) ADOSH-SF – Element 2 – Risk Management.
(iii) Law No. (5) of 2016 Concerning Control of Groundwater in Abu Dhabi, and its
bylaws;
(b) Employers shall undertake their specific roles and responsibilities in accordance with
the following:
(i) prior to the commencement of any construction work, an assessment is carried
out by a competent person, and appropriate control measures in line with this
CoP are undertaken;
(ii) documented safe systems of work are prepared which are designed to ensure
that the construction works are systematically planned and appropriate work
methods and procedures are in place;
(iii) all underground services searches are initiated and validated (including through
securing drawings from utility services providers);
(iv) any historical, archaeological or geological items are safeguarded and/or
documented as per requirements of the relevant authorities;
(v) providing accurate and competent technical advice on the work;
(vi) deciding the most appropriate drilling and construction method to be used;
(vii) ensuring that the quantity and quality of materials used are appropriate for the
job;
(viii) leaving the site in a safe, clean and tidy manner and free from contamination;
(ix) securing all relevant information on the work areas to be drilled. This includes
site surveys, plans of services and information on the nature and location of
hazardous materials;
(x) obtaining all necessary work permits, no objection certificates, authorizations
and providing all necessary notifications concerning the work;
(xi) nominating a person to supervise the work at all times and implement the
construction safety operations. This person shall be competent in the type of
drilling and well construction work needed for the particular project and
experienced in the implementation of safe work procedures;
(xii) providing appropriate amenities for employees, in compliance with
ADOSH-SF –
CoP – 8.0 – General Workplace Amenities;
(xiii) providing appropriate first aid and emergency procedures / services;

ADOSH-SF – Codes of Practice - CoP 46.1 – Construction of Water Wells
Version 4.0 – 15 th July 2024
Page 8 of 22
(xiv) ensuring all persons employed are physically fit and that all persons and all plant
operators and banksmen are at least 18 years old; and
(xv) taking all reasonably practicable precautions at all times during the progress of
the work to prevent tampering with the well or the of foreign material.
3.1.2 Principal Contractors
(a) In the case the project is controlled by the Building and Construction Sector, Principal
Contractors shall undertake their roles and responsibilities in accordance with the
general requirements of
ADOSH-SF – CoP 53.0 – OSH Management during
“Construction Work”.
(b) Principal Contractors shall undertake their specific roles and responsibilities in
accordance with the following:
(i) the well drilling contractors (entities) are licensed by the authorities responsible
for permitting of wells in the emirate and have the competent / qualified staff;
(ii) the well drilling contractors (entities) have been provided with all available
descriptions of the site, including drawings, site surveys, other existing wells
and information on the nature and location of hazardous materials;
(iii) all relevant authorities are notified and all necessary NOC’s and consents are
obtained before work commences;
(iv) the location of all utility services is known and protected;
(v) appropriate control measures are implemented; and
(vi) the workplace is secured.
3.1.3 Employees
(a) Employees shall undertake their roles and responsibilities in accordance with the
general requirements of
ADOSH-SF – Element 1 – Roles, Responsibilities and Self-
Regulation Section 3.2.7.
(b) Employees shall undertake their specific roles and responsibilities in accordance with
the following:
(i) carry out their work in accordance with the drilling and construction procedures;
(ii) report identified hazards and risks; and
(iii) use equipment in accordance with the instruction and training provided.

ADOSH-SF – Codes of Practice - CoP 46.1 – Construction of Water Wells
Version 4.0 – 15 th July 2024
Page 9 of 22
3.2 Planning and Assessment
3.2.1 Planning
(a) Employers shall ensure that:
(i) an assessment of the various risks is undertaken and systems of work are
established which are safe to all parties involved or affected including the public;
(ii) appropriate control measures are implemented in order to manage activities
safely and without risk to health; and
(iii) in case the project is controlled by the Building and Construction Sector,
associated safe systems of work and site rules are included in the Safety and
Health Construction Management Plan (OSH-CMP) in accordance with
ADOSH-
SF – CoP 53.0 – OSH Management during “Construction Work”.
3.2.2 Assess Site’s Work Requirements
(a) Before any drilling and construction work is carried out employers shall ensure a
competent person assesses the work requirements for the site.
(b) Following the assessment, the competent person shall prepare documented safe
systems of work.
3.2.3 Documented Safe Systems of Work
(a) Employers shall ensure the documented safe systems of work are designed to ensure
that:
(i) drilling operations and construction works are systematically planned; and
(ii) appropriate safe work practices and control measures are in place.
3.3 General Construction Requirements
3.3.1 Permits and other Requirements
(a) The employer / drilling contractor shall comply with all Federal and Local requirements,
including but not limited to the requirements of authorities responsible for permitting
of wells in the emirate.
(b) Only drilling contractors (entities) licensed for the class of work proposed and for the
drilling method to be used shall carry out work on water wells.
(c) An appropriately qualified driller shall be on site at all times to supervise well
construction activities.
(d) The owner or legal occupier of the land on which a well is to be constructed shall
obtain all the permits from authorities responsible for permitting of wells in the
emirate. Work shall not commence on a well until such approval(s) has been obtained.
(e) The driller shall be in possession of the well permit(s) before commencing any work
and comply with the conditions relating to the particular well. The well permit(s) will
stipulate the nature of the work and the reporting requirements.

ADOSH-SF – Codes of Practice - CoP 46.1 – Construction of Water Wells
Version 4.0 – 15 th July 2024
Page 10 of 22
3.3.2 Well Design and Drilling Method
(a) The well design shall consider:
(i) intended purpose of the well;
(ii) geological and hydrogeological conditions, including the groundwater quality;
(iii) being appropriate to protect the aquifer; and
(iv) drilling methods and construction methods.
(b) The drilling methods and techniques utilized shall consider the expected
hydrogeological conditions.
(c) Drillers shall not contract or attempt works that could be reasonably expected to
exceed the capabilities of the drill plant and equipment to be used.
(d) If required by a relevant authority, representative formation samples shall be taken to
determine the nature and type of strata encountered. Information gained from
formation samples influences the:
(i) casing size and length;
(ii) selection of casing and screen material;
(iii) aperture of the well screen, and the gradation of the gravel pack; and
(iv) well construction methods.
3.3.3 Protection of the Well and Groundwater Supply
(a) Positioning, construction and operation of wells shall consider:
(i) possible sources of contamination;
(ii) protection of the headwork’s from natural and accidental damage;
(iii) underground and overhead services and utilities; and
(iv) minimizing damage to property, infrastructure, roads, ground water quality and
the environment.
(b) All drilling equipment shall be disinfected to prevent the transfer of microbiological
organisms (bacteria) between sites.
(c) Groundwater samples shall be taken to provide a guide to water quality encountered
during drilling operations. Determining water quality shall impact on the:
(i) suitability of the well for the intended purpose and position;
(ii) construction methods;
(iii) selection of materials; and
(iv) aquifer separation methods.
(d) Drilling fluids shall be selected and managed to:
(i) protect ground water quality;

ADOSH-SF – Codes of Practice - CoP 46.1 – Construction of Water Wells
Version 4.0 – 15 th July 2024
Page 11 of 22
(ii) facilitate the drilling process;
(iii) ensure the removal of cuttings from the well; and
(iv) minimize the damage to the formations and the environment.
(e) The use of drilling fluid additives shall be in accordance with the manufacturer’s
recommendations and any international standards prescribed by Federal / Local
relevant authorities.
(f) Material Safety Data Sheet (MSDS) shall be available on the drill site for all materials
and products used.
(g) Chemicals or other substances that could leave a residual toxicity shall not be added
to the drilling fluid.
(h) Fresh non-polluted water (or if this is not possible the best quality water that is
reasonably available) shall be used as the base fluid / make-up water for all water well
drilling fluid preparations.
(i) The conductivity and pH values of all make-up waters shall be measured and recorded.
(j) A well completion report shall be developed and submitted to authorities responsible
for permitting of wells in the emirate, as per the well permit requirements.
3.3.4 Well Characteristics
(a) Wells shall be sufficiently plumb and straight to ensure that there will be no
interference with the installation, alignment, operation or removal of the pump.
(b) Well screens shall comply with relevant Federal and Local requirements.
(c) Well casings and joints shall:
(i) prevent the collapse of the strata penetrated;
(ii) prevent backflow;
(iii) assist in construction and sealing, and prevent intermixing;
(iv) be strong enough to withstand installation, construction and operational
pressures;
(v) provide access to the water-producing zone;
(vi) be of sufficient size to act as a safe housing for the pump selected for the hole;
and
(vii) provide an adequate operational life.
(d) Casing joints shall be watertight and have at least the same structural integrity as the
casing.
(e) The selected casing material and overall diameter of the well casing shall be sufficient
to accommodate the size of the pump that has been selected. It shall consider:
(i) the efficiency of the pumping unit;

ADOSH-SF – Codes of Practice - CoP 46.1 – Construction of Water Wells
Version 4.0 – 15 th July 2024
Page 12 of 22
(ii) the expected pump life;
(iii) the extra clearance required in the event that the casing is not sufficiently
straight;
(iv) the possibility of welds and other fasteners projecting inside the joints of the
casing; and
(v) any potential corrosion issues.
(f) The casing and casing joints shall withstand the pressures imposed during the
installation and operation of a well.
(g) All casing joints shall be aligned, secure and leak-proof.
(h) The casing material used shall comply with the manufacturer’s requirements and any
international standards prescribed by Federal / Local relevant authorities.
3.3.5 Well Sealing
(a) All wells shall be sealed to protect the production zone against contamination. This
also includes the annular space between the casings and the well hole. In multiple
aquifer wells there shall also be a seal between the aquifers and permeable zones to
prevent intermixing,
(b) All wells shall be sealed from the surface to not less than 5 meters deep or, where the
‘production zone’ is less than 5 meters below ground level, the sealing shall be from 1
meter above the production zone to the surface.
(c) When sealing the surface control casing in artesian wells, the casing shall be:
(i) seated at least 10 meters into impermeable strata, and grouted from the shoe
to the surface; and
(ii) sealed with cement grout having a minimum annular thickness of 20 mm above
the maximum diameter of the casing (e.g., a coupling or shoe). This can be
obtained using centralisers.
(d) Wells drilled to provide access to aquifers for the injection of water shall be sealed
with cement grout from the top of the production zone to the surface.
(e) Multi-port monitoring wells intersecting more than one aquifer shall be cased and
sealed with cement grout from the top of the lowest aquifer system back to the
surface.
(f) There shall be a minimum thickness of 15 mm of grout seal around the outside of the
production casing.

ADOSH-SF – Codes of Practice - CoP 46.1 – Construction of Water Wells
Version 4.0 – 15 th July 2024
Page 13 of 22
3.3.6 Well Completion, Headwork’s and Site Restoration
(a) All flowing wells shall be fitted with appropriate headwork to control the flow of
water.
(b) All flowing wells shall be fitted with an appropriate identification / code plate, as per
requirement of authorities responsible for permitting of wells in the emirates.
(c) Flowing wells shall be fitted with a full diameter main isolating valve to assist future
well maintenance and rehabilitation.
(d) Headwork components shall comply with the manufacturer’s requirements and any
international standards prescribed by Federal / Local relevant authorities.
(e) The protruding casing shall be completed so that it:
(i) is protected from accidental damage;
(ii) is protected from environmental conditions; and
(iii) prevents surface run-off potentially contaminated fluids from entering the well.
(f) Well casings shall be capped with an appropriately threaded, flanged or welded cap, or
a compression seal.
(g) After completion of drilling operations and well construction the site shall be restored
as close as reasonably practicable to its original condition.
3.3.7 Well Maintenance and Rehabilitation
(a) The rehabilitation of any well shall be carried out in accordance with the requirements
of authorities responsible for permitting of wells in the emirate and other relevant
authorities’ requirements.
(b) The standards set down for constructing new water wells also apply to the
rehabilitation of existing water wells.
(c) Owners of wells shall ensure appropriate preventative maintenance is performed on
all mechanical components (e.g., headwork’s and pumps), as per the manufacturer’s
requirements.
(d) The structural integrity of the well shall be regularly inspected by a competent person,
as part of a preventative maintenance program. Intervals include:
(i) at a minimum of once every 6 months for drinking water supply wells,
monitoring / observation wells and government owned well fields;
(ii) at a minimum of once every 12 months for all other wells.
(e) This inspection shall also include a thorough examination of the casing condition to
identify any deterioration, damage, holes, etc.
(f) Maintenance tasks shall not result in changes to the physical structure of the well.

ADOSH-SF – Codes of Practice - CoP 46.1 – Construction of Water Wells
Version 4.0 – 15 th July 2024
Page 14 of 22
(g) Rehabilitation of wells may change the structure of the well. Therefore well
rehabilitation shall only be performed by a licenced well drilling contractor (entity), and
a permit is obtained to perform the work.
(h) Rehabilitation of wells can include:
(i) relining the well with a new casing;
(ii) in situ repairs;
(iii) deepening / enlarging well;
(iv) repairing the screens;
(v) removing and replacing the casing; and
(vi) sealing a zone.
3.3.8 Well Decommissioning
(a) All wells are to be decommissioned as per the requirements of authorities responsible
for permitting of wells in the emirate.
(b) Decommissioning / backfilling report shall be prepared and submitted to the
authorities responsible for permitting of wells in the emirate, including returning the
well identification / code plates.
(c) All wells and test holes that are to be decommissioned shall be permanently sealed to
prevent:
(i) the entry of any surface fluids and contaminants;
(ii) the intermixing of fluids and pressures between aquifers; and
(iii) injury and harm to people, animals and the environment.
(d) Any well or hole that is to be permanently decommissioned shall be sealed and filled
in such a manner to prevent vertical movement of water in the well, including water
in the annular space surrounding the casing. The water should be permanently
confined to the specific zone in which it originally occurred.
(e) All test holes, test wells or failed wells shall be decommissioned by grout sealing as if
they were an operational well, as soon as possible after drilling operations are
complete.
(f) The sealing material shall consist of one or more of the following:
(i) grout;
(ii) bentonite grout;
(iii) bentonite pellets/chips; and
(iv) concrete.
(g) Fill material shall consist of uncontaminated sand, coarse stone, clay or drill cuttings.

ADOSH-SF – Codes of Practice - CoP 46.1 – Construction of Water Wells
Version 4.0 – 15 th July 2024
Page 15 of 22
(h) The seals shall be set in impermeable strata immediately above and below each
aquifer formation on the well. For non-flowing wells, a minimum of 10 meters of grout
plug shall be set for a seal.
(i) At a minimum, a concrete or grout surface seal to a minimum depth of 5 meters shall
be installed in all decommissioned wells and/or holes.
3.4 Plant and Equipment
(a) All plant and equipment are to be certified and tested before beginning operations.
(b) Employers shall ensure compliance of all plant / machines / equipment to
ADOSH-SF –
CoP – 36.0 – Plant and Equipment and
ADOSH-SF – CoP 34.0 – Safe Use of Lifting
Equipment and Lifting Accessories.
3.5 Machine Guarding
(a) Employers shall ensure the provision of fixed guards enclosing every dangerous,
moving or rotating component of all plant / machinery / equipment to the extent that
is reasonably practicable.
(b) Employers shall ensure that all plant / machines / equipment are in line with the
requirements of
ADOSH-SF – CoP 47.0 – Machine Guarding.
3.6 Visual and Hand Signals
(a) Employers shall ensure:
(i) signals to machine operators are given only by competent persons; and
(ii) compliance to ADOSH-SF – CoP 17.0 – Safety Signage and Signals.
3.7 Lone Working and/or in Remote Locations
(a) Employers shall ensure that no lone working is permitted. A team with two persons as
a minimum with a safe form of communication between them shall be used for the
work.
(b) Employers shall ensure that all communication systems are in compliance with the
requirements of
ADOSH-SF – CoP 30.0 – Lone Work and/or in Remote Locations.
3.8 Hazardous Substances
(a) Where hazardous substances are handled, employers shall ensure compliance with the
requirements of
ADOSH-SF – CoP 1.0 – Hazardous Substances and
ADOSH-SF – CoP 2.0
– Personal Protective Equipment.

ADOSH-SF – Codes of Practice - CoP 46.1 – Construction of Water Wells
Version 4.0 – 15 th July 2024
Page 16 of 22
3.9 Waste Management
(a) All discharged wastewater shall be disposed of in compliance with relevant
authorities’ requirements, in a manner that will not negatively affect the environment
or the community.
(b) Any cement, drilling fluids, containers, and disinfecting chemicals shall be neutralised
or disposed of in an appropriate manner in compliance with the manufacturers’
recommendations and any standards prescribed by relevant Federal / Local
authorities.
(c) Cuttings, spoils and other wastes shall be handled and disposed of in compliance with
ADOSH-SF – CoP 54.0 – Waste Management.
3.10 Dust and Toxic Gases
(a) Where dust or toxic gases are encountered (e.g., carbon mono oxide or hydrogen
sulphide under certain drilling conditions), employers shall ensure compliance with the
requirements of
ADOSH-SF - CoP 2.0 – Personal Protective Equipment.
3.11 Heat Stress and Exhaustion
(a) Mechanisation, ventilation and job rotation shall be arranged to reduce the risk of heat
stress and exhaustion.
(b) Appropriate supplies of cold potable water shall be made available.
(c) Employers shall comply with the requirements of
ADOSH-SF – CoP 11.0 – Safety in the
Heat.
3.12 Noise and Vibration
(a) Employers shall ensure all plant / machinery and equipment is selected on the basis of
risk assessment to be designed to eliminate or reduce the noise at source with
minimum operator exposure.
(b) Thereafter employers shall establish a management system that will:
(i) confirm the appropriateness of the noise and vibration controls;
(ii) continually identify significant residual noise sources; and
(iii) ensure regular maintenance checks and replacement or repair.
(c) Employers shall ensure compliance to
ADOSH-SF – CoP 3.0 – Occupational Noise and
ADOSH-SF - CoP 3.1 – Vibration.

ADOSH-SF – Codes of Practice - CoP 46.1 – Construction of Water Wells
Version 4.0 – 15 th July 2024
Page 17 of 22
3.13 Lighting
(a) Employers shall ensure that:
(i) general lighting levels are such that any hazards can readily be seen. Higher
lighting levels shall be provided locally, particularly near machinery and in
working areas;
(ii) where machinery with moving parts or edges is used, the lighting source shall
not create a stroboscopic effect;
(iii) the lighting scheme shall be designed to minimize glare; and
(iv) where color recognition is an important factor, the type of light source shall be
carefully considered to not affect normal color perception.
3.14 First Aid
(a) Employers shall ensure that:
(i) competent persons, trained in first aid and capable of responding rapidly to any
incident, are available on each shift during working hours. Refer to
ADOSH-SF –
4.0 – First Aid and Emergency Medical Treatment;
(ii) all personnel are informed that, in the event of serious injury, a casualty shall be
moved only by a trained first-aider, unless there is the immediate risk of further
injury; and
(iii) appropriate first aid boxes are provided, designed to protect the contents as far
as reasonably practicable from damp and dirt. Boxes shall be clearly identified,
readily accessible to working areas and in the charge of designated first-aiders.
3.15 Fire Prevention and Control
(a) Employers shall ensure that:
(i) open flames and fires are prohibited in construction areas except as permitted
for welding, cutting, or other hot work operations;
(ii) smoking is prohibited at all times and notices are prominently displayed;
(iii) appropriate fire extinguishers or extinguishing means are available; and
(iv) oil, grease, and diesel fuel stored underground is kept in tightly sealed
containers in appropriate areas.
(b) Employers shall ensure compliance to:
(i) ADOSH-SF – Element 6 – Emergency Management; and
(ii) ADOSH-SF – CoP 28.0 – Hot Work Operations.

ADOSH-SF – Codes of Practice - CoP 46.1 – Construction of Water Wells
Version 4.0 – 15 th July 2024
Page 18 of 22
3.16 Emergency Management
(a) Employers shall ensure compliance to
ADOSH-SF – Element 6 – Emergency
Management and the applicable local and federal regulations set by relevant
authorities.

ADOSH-SF – Codes of Practice - CoP 46.1 – Construction of Water Wells
Version 4.0 – 15 th July 2024
Page 19 of 22
4. References

Minimum Construction Requirements for Water Bores in Australia –
February 2012 – Edition 3 – ISBN 978-0-646-56917-8

ADOSH-SF – Codes of Practice - CoP 46.1 – Construction of Water Wells
Version 4.0 – 15 th July 2024
Page 20 of 22
5. Document Amendment Record
Version Revision Date Description of Amendment
Page/s Affected
4.0
15 th July 2024
System acronym updated from OSHAD-SF
to ADOSH-SF to accurately reflect
document title
Throughout
Change from OSHAD to ADPHC
Change of Logo
Minor editorial changes throughout the
document without changing requirements.
Title of Mechanism 7.0 updated to ADOSH-
SF – Mechanism 7– Occupational Safety
and Health Practitioner and Service
Provider Registration.
OSHAD-SF - Mechanism 8.0 - OSH
Practitioner Registration deleted

ADOSH-SF – Codes of Practice - CoP 46.1 – Construction of Water Wells
Version 4.0 – 15 th July 2024
Page 21 of 22